Meyer Turku talks layoffs, sees one large cruise ship/year, not two, swings to 2019 loss

Meyer Turku shipyard plans layoffs, said future production will stick to one large cruise ship a year, not two as hoped, and posted a 2019 loss.

Anne Kalosh, Editor, Seatrade Cruise News & Senior Associate Editor, Seatrade Cruise Review

April 28, 2020

2 Min Read
CRUISE Mardi Gras at Meyer Turku
Carnival's Mardi Gras, seen here at its float-out, is due for delivery later this yearPHOTO: MEYER TURKU

450 layoffs and changes for 900 others

Talks begun about temporary layoffs in the middle of March have now moved to a deeper level with plans to permanently lay off 450 people while another 900 are affected by other measures. These include temporary layoffs of different lengths, work time adjustments and other arrangements. All personnel groups and levels are part of the negotiations.

'The corona pandemic has changed the situation unexpectedly and totally. We are facing the fact that the corona-caused pause in cruising requires stretching the orderbook. We are currently discussing the details with our customers. This new situation will force us to take painful adaptation measures to secure a sustainable future for Finnish cruise ship building and the network,' Meyer Turku CEO Jan Meyer said.

One cruise ship per year

' ... We have to adjust to that new future,' he continued. 'Instead of a further ramp-up from one to two large ships delivered per year until 2023, the estimation is now that Turku shipyard will in the future build one large cruise ship per year and not further ramp-up.'

Deliveries under negotiation

The exact changes to the building and delivery times of the seven ships in Meyer Turku's orderbook — which reached until 2025 — are still under negotiations with customers.

Carnival Cruise Line's Mardi Gras is due for delivery this year. Costa Toscana is scheduled in 2021, Royal Caribbean International's first Icon-class ship and a Mardi Gras sister in 2022, TUI Cruises' Mein Schiff 7 in 2023, a second Icon ship in 2024 and a third in 2025.

2019 loss on Costa Smeralda delay

Meyer Turku swung to a €109.7m loss in 2019 on the delay of Costa Smeralda, caused by issues ramping up to handle the size and complexity of the project. This compared to a €29m profit in 2018.

Net sales were €1,141.8m, up from €967m the year before.

The number of personnel averaged 2,386 during 2019, compared to 2,205 in 2018.

About the Author

Anne Kalosh

Editor, Seatrade Cruise News & Senior Associate Editor, Seatrade Cruise Review

Anne Kalosh covers global stories, reporting both breaking and in-depth news on cruising's significant people, places, ships and trends. A sought-after expert on cruising, she has moderated conferences around the world, including the high-profile State of the Industry panel at Seatrade Cruise Global. She created and led the acclaimed itinerary-planning case study for Seatrade's cruise master classes held at Cambridge and Oxford universities. She has been the cruise columnist for AFAR.com, and her freelance stories have appeared in a wide range of publications, from The New York Times to The Miami Herald.

The latest cruise news, analysis and more straight to your inbox
Get the free newsletter read by industry experts

You May Also Like